We are the very first contractor completed and handover the roads "100000km" rural roads rehabilitation project in Eastern Province in last year. Our well dedicated team achieved the targets in Time.

01. Asian Development Bank Funded - Second Integrated Road Investment Program - Eastern iRoad

Province

Eastern Province

Engineer

EGIS International and Greentech Ltd JV

Contractor

SJT Engineering Pvt Ltd

Funding Agents

Asian Development Bank

Package 01 - AM 01 Completed

AM-01 Road Package will rehabilitate about 80km length of rural roads located in Ampara district, where 25 roads to be rehabilitated in Dehiaththakandiya and Padiyathalawa area. The project is executed by the Road Development Authority under the ministry of Roads and Highways, which is funded by the Asian Development Bank.

Contract Package No

RDA/ADB/iROAD-2(EP)/NCB/AM-01

Accepted Contract Amount

SLR 2,191,974,580.31

Total Road Length

80km

Total No. of Roads

25

Commencement date

25th Sept 2019

Completion Date

24th Sept 2021

Time for completion

730 days

Progress

Surveying & Design

100%

Cleaning & Grubbing

100%

Earth Work

100%

Road Pavement

100%

Culvert & Retaining Structure

100%

Drains

100%

Incidental Work

100%

Achievements

  • The first project completed in the Eastern Province among all well reputed contractors
  • Engineer and as well as the Employer highly satisfied and greatly appreciated our team
  • No any major accidents or fatal accidents recorded during the project period
  • Giving priority to the Corporative Social Responsibilities, many social programs were arranged and successfully conducted
  • Eight Fruitful tree plantation programs conducted where we planted more than 1000 trees

Package 02 - AM 02 Completed

AM-02 Road Package will rehabilitate about 85km length of rural roads located in Ampara district, where 31 roads to be rehabilitated in Uhana and Mahaoya area. The project is executed by the Road Development Authority under the ministry of Roads and Highways, which is funded by the Asian Development Bank.

Contract Package No

RDA/ADB/iROAD-2(EP)/NCB/AM-02

Accepted Contract Amount

SLR 2,411,155,243.20

Total Road Length

85km

Total No. of Roads

29

Commencement date

25th Sept 2019

Completion Date

24th Sept 2021

Time for completion

730 days

Progress

Surveying & Design

100%

Cleaning & Grubbing

100%

Earth Work

100%

Road Pavement

100%

Culvert & Retaining Structure

100%

Drains

100%

Incidental Work

100%

Achievements

  • The second project completed in the Eastern Province among all well reputed contractors. (Firstly handed over AM01, which is also done by SJT)
  • Engineer and as well as the Employer highly satisfied and greatly appreciated our team
  • No any major accidents or fatal accidents recorded during the project period
  • Giving priority to the Corporative Social Responsibilities, many social programs were arranged and successfully conducted
  • Eight Fruitful tree plantation programs conducted where we planted more than 1000 trees

02. Rehabilitation / Improvements of Roads Under the Implementation of 100,000 km Alternative Road System Under the Government Policy Statement of "Vistas of Prosperity and Splendour"

Contractor

SJT Engineering Pvt Ltd

Engineer

Road Development Authority

Package 01 - P 05 Completed

Rehabilitation/ Improvements of 100,000 km alternative rural roads project

Contract No

MORH/RDA/LBRRP/EP/AMP/2020/P05(QA)

Contract Value

SLR 162,510,125.69

Total Road Length

10km

Total No. of Roads

6

Time for completion

273 days

Achievements

  • The first project completed in the Eastern Province among all well reputed contractors.
  • Employer highly satisfied and greatly appreciated our team
  • No any major accidents or fatal accidents recorded during the project period
  • Defects Liability Period successfully conceded

Package 02 - P 06 Completed

Rehabilitation/ Improvements of 100,000 km alternative rural roads project

Contract No

MORH/RDA/LBRRP/EP/AMP/2020/P06(QA)

Contract Value

SLR 185,387,623.33

Total Road Length

10km

Total No. of Roads

4

Time for completion

273 days

Achievements

  • The first project completed in the Eastern Province among all well reputed contractors.
  • Employer highly satisfied and greatly appreciated our team
  • No any major accidents or fatal accidents recorded during the project period
  • Defects Liability Period successfully conceded

03. RT 09 - Rehabilitation/ Improvement and maintenance of 18.35 km Rural roads in Badulla District

Completed

Province

Uva Province

Engineer

Road Development Authority

Accepted Contract Amount

SLR 1,031,817,631.20

Total Road Length

20.20km

Total No. of Roads

6

Commencement date

7th March 2022

Completion Date

30th Sep 2024

Progress

Clearing and Grubbing

100%

Roadway Excavation

100%

Embankment Construction

100%

Aggregate Base Course Paving

100%

Priming

100%

Asphalting

100%

Incidental Construction

100%

Achievements

  • The first contractor who completed the roads and started to hand over the roads
  • Employer highly satisfied and greatly appreciated our team
  • No any major accidents or fatal accidents recorded to the date
  • Successfully conducted and done the CSR programs
  • Three Tree plantations programs done and over 750 trees planted
  • Awarded Additional Road works located in Haldumulla area including Kalupahana to Bambaraknada Waterfall road and Idalgashinna Road

04. World Bank funded project - Inclusive Connectivity and Development Project

Completed

Province

Uva Province

Engineer

Road Development Authority

Funding Agents

World Bank

Inclusive Connectivity and Development Project

LOT-2 Road Package will rehabilitate about 14.20km length of rural roads located in Siyabalanduwa Medagama and Monaragala Divisional Secretariat in Monaragala District, Uva Province.The project is executed by the Road Development Authority under the ministry of Transport and Highways, which is funded by the world Bank.

Contract Package No

LK-RDA-251205-CW-LOT 2

Accepted Contract Amount

SLR 658,808,947.51

Total Road Length

14.20km

Total No. of Roads

05

Commencement date

10th July 2023

Completion Date

09th Feb 2025

Time for completion

19 Months

Progress

Surveying & Design

100%

Cleaning and Grubbing

100%

Earth Work

100%

Road Pavement

100%

Culvert & Retaining Structure

100%

Drains

100%

Incidental Work

100%

Achievements

  • Project Completed earlier than 6 months for original completion date
  • Engineer and as well as the Employer highly satisfied and greatly appreciated our team
  • No any major accidents or fatal accidents recorded during the project period
  • Giving priority to the Corporative Social Responsibilities, many social programs were arranged and successfully conducted
  • Two tree plantation programs conducted where we planted more than 350 trees

05. World Bank funded project - Inclusive Connectivity and Development Project

In progress

Province

Southern Province

Engineer

Road Development Authority

Funding Agents

World Bank

Inclusive Connectivity and Development Project

Rehabilitation Improvement and Maintenance of 12.3 km Rural Roads in Sooriyawewa and Hambanthota District Divisional Secretariat in Hambanthota District, Southern Province .The project is executed by the Road Development Authority under the ministry of Transport and Highways, Ports and Aviation. which is funded by the World Bank.

Contract Package No

LK-RDA-251207-CW-LOT 3

Accepted Contract Amount

SLR 390,339,448.04

Total Road Length

12.30km

Total No. of Roads

07

Commencement date

8th April 2024

Completion Date

09th April 2025

Time for completion

12 Months

Progress

Surveying & Design

100%

Cleaning and Grubbing

100%

Earth Work

85 100 %

Road Pavement

75 100 %

Culvert & Retaining Structure

75 100 %

Drains

75 100 %

Incidental Work

0 100 %

Achievements

  • Engineer and as well as the Employer highly satisfied and greatly appreciated our team
  • No any major accidents or fatal accidents recorded up to now
  • Giving priority to the Corporative Social Responsibilities, many social programs were arranged and successfully conducted

06. World Bank funded project - Inclusive Connectivity and Development Project

In progress

Province

North Central Province

Engineer

Road Development Authority

Funding Agents

World Bank

Inclusive Connectivity and Development Project

Rehabilitation Improvement and Maintenance of 21.8 km Rural Roads in Dimbulagala, Dehiaththakandiya and Elahara Divisional Secretariate in Polonnaruwa District in North Central Province. The project is executed by the Road Development Authority under the ministry of Transport and Highways, Ports and Aviation, which is funded by the World Bank.

Contract Package No

LK-RDA-353937-CW-LOT 3

Accepted Contract Amount

SLR 609,755,991.60

Total Road Length

21.8km

Total No. of Roads

06

Commencement date

30th September 2024

Completion Date

31st January 2026

Time for completion

488 days

Progress

Surveying & Design

100%

Cleaning and Grubbing

80 100 %

Earth Work

60 100 %

Road Pavement

17 100 %

Culvert & Retaining Structure

5 100 %

Drains

2 100 %

Incidental Work

0 100 %