We are the very first contractor completed and handover the roads "100000km" rural roads rehabilitation project in Eastern Province in last year. Our well dedicated team achieved the targets in Time.

01. Asian Development Bank Funded - Second Integrated Road Investment Program - Eastern iRoad

Province

Eastern Province

Engineer

EGIS International and Greentech Ltd JV

Contractor

SJT Engineering Pvt Ltd

Funding Agents

Asian Development Bank

Package 01 - AM 01 Completed

AM-01 Road Package will rehabilitate about 80km length of rural roads located in Ampara district, where 25 roads to be rehabilitated in Dehiaththakandiya and Padiyathalawa area. The project is executed by the Road Development Authority under the ministry of Roads and Highways, which is funded by the Asian Development Bank.

Contract Package No

RDA/ADB/iROAD-2(EP)/NCB/AM-01

Accepted Contract Amount

SLR 2,191,974,580.31

Total Road Length

80km

Total No. of Roads

25

Commencement date

25th Sept 2019

Completion Date

24th Sept 2021

Time for completion

730 days

Progress

Surveying & Design

100%

Cleaning & Grubbing

100%

Earth Work

100%

Road Pavement

100%

Culvert & Retaining Structure

100%

Drains

100%

Incidental Work

100%

Achievements

  • The second project completed in the Eastern Province among all well reputed contractors. (Firstly handed over AM01, which is also done by SJT)
  • Engineer and as well as the Employer highly satisfied and greatly appreciated our team
  • No any major accidents or fatal accidents recorded during the project period
  • Giving priority to the Corporative Social Responsibilities, many social programs were arranged and successfully conducted
  • Eight Fruitful tree plantation programs conducted where we planted more than 1000 trees

Package 02 - AM 02 Completed

AM-02 Road Package will rehabilitate about 85km length of rural roads located in Ampara district, where 31 roads to be rehabilitated in Uhana and Mahaoya area. The project is executed by the Road Development Authority under the ministry of Roads and Highways, which is funded by the Asian Development Bank.

Contract Package No

RDA/ADB/iROAD-2(EP)/NCB/AM-02

Accepted Contract Amount

SLR 2,411,155,243.20

Total Road Length

85km

Total No. of Roads

29

Commencement date

25th Sept 2019

Completion Date

24th Sept 2021

Time for completion

730 days

Progress

Surveying & Design

100%

Cleaning & Grubbing

100%

Earth Work

100%

Road Pavement

100%

Culvert & Retaining Structure

100%

Drains

100%

Incidental Work

100%

Achievements

  • The second project completed in the Eastern Province among all well reputed contractors.
  • Engineer and as well as the Employer highly satisfied and greatly appreciated our team
  • No any major accidents or fatal accidents recorded during the project period
  • Giving priority to the Corporative Social Responsibilities, many social programs were arranged and successfully conducted
  • Eight Fruitful tree plantation programs conducted where we planted more than 1000 trees

02. Rehabilitation / Improvements of Roads Under the Implementation of 100,000 km Alternative Road System Under the Government Policy Statement of "Vistas of Prosperity and Splendour"

Contractor

SJT Engineering Pvt Ltd

Engineer

Road Development Authority

Package 01 - P 05 Completed

Rehabilitation/ Improvements of 100,000 km alternative rural roads project

Contract No

MORH/RDA/LBRRP/EP/AMP/2020/P05(QA)

Contract Value

SLR 162,510,125.69

Total Road Length

10km

Total No. of Roads

6

Time for completion

273 days

Achievements

  • The first project completed in the Eastern Province among all well reputed contractors.
  • Employer highly satisfied and greatly appreciated our team
  • No any major accidents or fatal accidents recorded during the project period
  • Defects Liability Period successfully conceded

Package 02 - P 06 Completed

Rehabilitation/ Improvements of 100,000 km alternative rural roads project

Contract No

MORH/RDA/LBRRP/EP/AMP/2020/P06(QA)

Contract Value

SLR 185,387,623.33

Total Road Length

10km

Total No. of Roads

4

Time for completion

273 days

Achievements

  • The first project completed in the Eastern Province among all well reputed contractors.
  • Employer highly satisfied and greatly appreciated our team
  • No any major accidents or fatal accidents recorded during the project period
  • Defects Liability Period successfully conceded

03. RT 09 – Rehabilitation/ Improvement and maintenance of 18.35 km Rural roads in Badulla District

Province

Uva Province

Engineer

Road Development Authority

Accepted Contract Amount

SLR 1,031,817,631.20

Total Road Length

18.35km

Total No. of Roads

5

Time for completion

370 days

Progress

Clearing and Grubbing

70 100 %

Roadway Excavation

70 100 %

Embankment Construction

70 100 %

Aggregate Base Course Paving

70 100 %

Priming

70 100 %

Asphalting

70 100 %

Incidental Construction

60 100 %

Achievements

  • The first contractor who completed the roads and started to hand over the roads
  • Employer highly satisfied and greatly appreciated our team
  • No any major accidents or fatal accidents recorded to the date
  • Successfully conducted and done the CSR programs
  • Three Tree plantations programs done and over 750 trees planted